Saturday, November 21, 2009

Main House Update

The main house during the past few weeks had drywall and lath completed and is currently ready for texture and the start of stucco.

Doors and mill work should be ordered in this upcoming week.

The main entry door Honduras Mahogany has been installed along with the rear entry glass doors.

Cabinets are now entering their third week of fabrication and should be ready and delivery and installation will commence the second week of December.