Thursday, December 24, 2009
Interior Doors Arrived
Twenty five interior doors arrived and will be installed the first week of January 2010.
Friday, December 4, 2009
Thursday, December 3, 2009
All Drywall Taping and Texture Completed in Main House
As of Friday November 27, 2009 drywall, taping and texture has been completed in the main Technology Lake House.
We had a great week of weather in the sixty's each day
Stucco should start on the main house hopefully Monday December 7, 2009
We had a great week of weather in the sixty's each day
Stucco should start on the main house hopefully Monday December 7, 2009