Thursday, December 24, 2009

Interior Doors Arrived

Twenty five interior doors arrived and will be installed the first week of January 2010.

Friday, December 4, 2009

Kitchen Cabinets being placed into position


This week our cabinet maker started putting in place the main house kitchen cabinets.

Thursday, December 3, 2009

All Drywall Taping and Texture Completed in Main House

As of Friday November 27, 2009 drywall, taping and texture has been completed in the main Technology Lake House.

We had a great week of weather in the sixty's each day

Stucco should start on the main house hopefully Monday December 7, 2009