Sunday, April 4, 2010

Tile is being installed.

Tile was finished in the lower floor in the guest suite, guest kitchen and guest entry.

Tile is being installed in the master bedroom and master bathroom and should be finished by the end of this week April 9th.

Next will be the lower entry and hallway to the home theater.

Stucco is Finished

We finally had a week full of sunshine so the stucco color coat was applied to the balance of the house except where the ledge stone is going to be applied on the sides and the top of the living room.